Skip to main content

How to workability test of concrete by slump cone? What is true slump?What is zero slump? What is shear slump? What is Slump cone test?

Slump cone test: This test is performed to determine the workability of fresh concrete. 

Appratus: In this test we take a mould of cone shape which top dia is 100mm and bottom dia is 200mm and height is 3000mm. For the compaction of concrete we take a tamping rod of 16mm dia and 600mm length.

Procedure of slump cone test:

Clean the internal surface of the mould.

Fill the mould with concrete in four uniformly layers.

Tamp each layer with 25 strocks to the tamping rod.

Distribute the strocks uniformly over the entire cross sections of the mould.

The rod should be penetrate every underlaying layer.

Strike off excess concrete after the top layer with trowel.

Remove the mould slowly and vertically.

The concrete will slump or slide.

Measure the height of slump in mm.

Now, take a sample from ready mixed pland and experment proced acording to above procedure and compare its slump value with following conditions which are given below.

Find the workability of concrete by the slump value:

1. When the degree of workability - Extremly low

It is moisture earth.Slump value is 0 mm.

Compacting factor 0.65 to 0.70

Vee-Bee degree less than 20 secomd.

Its can be used for precast paving slabs. Its consitency

2. When the degree of workability - Very low. 

Its consitency is very dry concrete.

Slump value 0 to 25 mm

Compacting factor 0.70 to 0.80

Vee-Bee degree 12 to 20 secomd.

Its can be used for blinding concrete, shallow sections.

3. When the degree of workability - low

Its consitency is dry concrete.

Slump value 25 to 50 mmCompacting factor 0.80 to 0.85

Vee-Bee degree 6 to 12 secomd.

Its can be used for mass concreting, highly reinforced, slab sections, beams, columns, flors, hand placed pavement, canal lining, strip footings.

4. When the degree of workability - Medium.

Its consitency is plastic concrete.

Slump value 50 to 100 mm

Compacting factor 0.85 to 0.95

Vee-Bee degree 3 to 6 secomd.

Its can be used for heavely reinforced slab sections, beams, walls, columns, sleep form work.

Slump value 100 to 175 mm.

Compacting factor 95 to 1.

Vee-Bee degree 0 to 3 secomd.

Its can be used for trench fill and in site piling.

5. When the degree of workability - High

Its consitency is plastic concrete.

Slump value 50 to 100 mm

Compacting factor 0.85 to 0.95

Vee-Bee degree 3 to 6 secomd.

Its can be used for heavely reinforced slab sections, beams, walls, columns, sleep form work.

Slump value 100 to 175 mm.

Compacting factor 95 to 1.

Vee-Bee degree 0 to 3 secomd.

Its can be used for trench fill and in site piling.

6. When the degree of workability - Very high

Slump value >175 mm.

Used as termie concrete.

Comments

Popular posts from this blog

What is conventional formwork system? What is procedure to use?

Formwork: Formwork is dye or mould used to shape wet concrete until it sets and attains sufficient strength to carry its own weight and retains its shape.There are various types shuttering material used for construction work. 1. Conventional formwork system 2. Mivan formwork system. 1. Conventional formwork system: Terminology used in conventional formwork system- 1. Formwork(shuttering) : Mould to contain the wet concrete in the desired shape. 2. False work(staging or centering ): Temporary structure use to support a permanent structure during erection and until it becomes self supporting. 3. Scaffolding(Paranja): Light structure 'Framework' for easy excess of workmen. 4. Striking(Stripping): scientific dismentling and removing formwork. 5. Sheeting(Sheathing): Supporting membrane in contact with the wet concrete. 6. Joist(Batten ): Horizontal member supporting sheeting (slab and beam). 7. Bearer(Runner ): Horizontal member supporting joista. 8. Pro

How many number of bricks needed in 1 square meter?

Required of bricks in 1 square meter: Generally, the size of bricks at site we found that, 230mm length, 115mm width, and 65mm thick.  If we assume 10mm thick mortar then the nominal length will be 240mm and thickness will be 75mm. Diamention change, mm to meter Length=240mm=0.24m Thickness=75mm=0.075m Now, we are calculating the area of 1 brick                            = 0.240×0.75                           = 0.01824  square meter Now, we are find nos. of bricks in 1 square meter Nos. of bricks= 1 square meter/ area of 1 brick Nos. of bricks=1/0.01824=55.55~ 56 nos.  If brick wall is 4 inch thick then, Nos. of bricks in 1 square meter = 56 nos. If brick wall is 9 inch thick then, Nos. of bricks in 1 square meter = 112 nos.  Variation in nos. bricks occure in following conditions: The number of bricks in 1 square meter are varies on following factors: The length of brick, thickness of brick and the thickness of mortar used in masonry work.  If the size of bricks increased and the th

What is concrete cube? How to test compressive strength of concrete by cube test?

Cube Test: In this test chque a compressive strength of concrete. Take a cube mould which dimentions are 150 mm×150 mm×150 mm (l×b×h) symultenouly. Also used a tamping rod of 16mm dia.Before the filling of cube mould apply the oil in the internal surface prolerly by which mould open eayly and surface be come smooth.On the cube writedown the casting date, grid number, footings, columns, beams, or slab. After 12 hours remove from mould and sink in quring pond. Generly we are cast 6 cubes, 3 cubes test after 7 days and 3 cubes test at 28 days. If you can test at 14 days then need to be cast of 9 cubes. In each test take 3 cubes and consider avrage value of all 3rd.After 7 days concrete cubes dry prolerly in the persence of sun. Weight the cube one by one and writedown. The each weight of concrete cube not less than 8.1 kg. How we proove that the weight of concrete cube should not be less than 8.1 kg. Given dimentions of cube are length =150mm=0.15m, width=150mm=0.15m, depth=150mm=0.15m, s