Skip to main content

What is conventional formwork system? What is procedure to use?

Formwork: Formwork is dye or mould used to shape wet concrete until it sets and attains sufficient strength to carry its own weight and retains its shape.There are various types shuttering material used for construction work.

1. Conventional formwork system

2. Mivan formwork system.

1. Conventional formwork system:

Terminology used in conventional formwork system-


1. Formwork(shuttering) : Mould to contain the wet concrete in the desired shape.

2. False work(staging or centering): Temporary structure use to support a permanent structure during erection and until it becomes self supporting.

3. Scaffolding(Paranja): Light structure 'Framework' for easy excess of workmen.

4. Striking(Stripping): scientific dismentling and removing formwork.

5. Sheeting(Sheathing): Supporting membrane in contact with the wet concrete.

6. Joist(Batten): Horizontal member supporting sheeting (slab and beam).

7. Bearer(Runner): Horizontal member supporting joista.

8. Prop cap: Seating for bearer.(axial load).

9. Prop: Vertical member supporting bearer.

10. Prop base: Seating for prop.(Punching shear)

11. Prop footing(Spreader): Member transferring all load on unyielding strata.

12. Wedge: Packing piece used for correct leveling and easy Striking of formwork.

13. Wailing or waling: Horizontal member resisting hydrostatic concrete load on Sheeting(Vertical wall). 

14. Stud: Vertical member resisting hydrostatic concrete load on Sheeting(wall).

15. Soldier: Vertical supporting member cantilevered from previous concrete.

16. (I): For column- Horizontal frame support encircling formwork.

(II) For slip form- Vertical frame support straddling inner and outer formwork.

17. Stop-end(Bulk head) : Vertical formwork to from a construction joint in concrete. 

18. Back from: Formwork to the top surface of a sloping slab.

19. Bracings: 

I. Horizontal - Member in two direction slenderness ratio. 

II. Diagonal - Member transferring horizontal and wind load through prop.

20. Tie bolt: Interconnecting two opposite formwork to resist for hydrostatic load.

21. Riband: Horizontal member laid flat to resist horizontal pressure from formwork.

22. Kicker(starter): Small height of wall or column cast along with the footing.

23. Shikanja: To Holden the two opposite formwork or to holde the two right angle formwork.

24. Four way head: To support to I-section beams below slab or beam bottom.

25. Tripod: To keep prop in exact plumb and position.

Comments

Popular posts from this blog

How many number of bricks needed in 1 square meter?

Required of bricks in 1 square meter: Generally, the size of bricks at site we found that, 230mm length, 115mm width, and 65mm thick.  If we assume 10mm thick mortar then the nominal length will be 240mm and thickness will be 75mm. Diamention change, mm to meter Length=240mm=0.24m Thickness=75mm=0.075m Now, we are calculating the area of 1 brick                            = 0.240×0.75                           = 0.01824  square meter Now, we are find nos. of bricks in 1 square meter Nos. of bricks= 1 square meter/ area of 1 brick Nos. of bricks=1/0.01824=55.55~ 56 nos.  If brick wall is 4 inch thick then, Nos. of bricks in 1 square meter = 56 nos. If brick wall is 9 inch thick then, Nos. of bricks in 1 square meter = 112 nos.  Variation in nos. bricks occure in following conditions: The number of bricks in 1 square meter are varies on following factors: The length of brick, thickness of brick and the thickness of mortar used in masonry work.  If the size of bricks increased and the th

What is concrete cube? How to test compressive strength of concrete by cube test?

Cube Test: In this test chque a compressive strength of concrete. Take a cube mould which dimentions are 150 mm×150 mm×150 mm (l×b×h) symultenouly. Also used a tamping rod of 16mm dia.Before the filling of cube mould apply the oil in the internal surface prolerly by which mould open eayly and surface be come smooth.On the cube writedown the casting date, grid number, footings, columns, beams, or slab. After 12 hours remove from mould and sink in quring pond. Generly we are cast 6 cubes, 3 cubes test after 7 days and 3 cubes test at 28 days. If you can test at 14 days then need to be cast of 9 cubes. In each test take 3 cubes and consider avrage value of all 3rd.After 7 days concrete cubes dry prolerly in the persence of sun. Weight the cube one by one and writedown. The each weight of concrete cube not less than 8.1 kg. How we proove that the weight of concrete cube should not be less than 8.1 kg. Given dimentions of cube are length =150mm=0.15m, width=150mm=0.15m, depth=150mm=0.15m, s

1000 वर्ग फीट मे मकान बनाने में कितना खर्च आएगा?

चुकीं हम निकाल चुके हैं कि,  1 वर्ग फीट मकान बनाने खर्च लगभग=1300 आता है,  इसलिए,  1000 वर्ग फीट जमीन मे मकान बनाने में कुल खर्च=1300×1000=1300000 रुपए आएगा ल अधिक जानकारी के लिए👉  1000 वर्ग फीट में मकान बनाने में कितना खर्च आएगा?